Chaos Is Back
Computerworld - We're losing ground. Only 28% of IT projects succeed these days, down from 34% a year or two ago. Outright failures -- IT projects canceled before completion -- are up to 18% from 15%. The remaining 51% of IT projects are "challenged" -- seriously late, over budget and lacking expected features.
Those numbers are from the just-completed Chaos report from The Standish Group. Standish has been doing this study since 1994, and ever since, we've been steadily improving our ability to deliver projects. A decade ago, only 16% of IT projects were successes. By last year, it was twice that. Now we're backsliding.
How did we get headed in the wrong direction?
When I talked to Standish Chairman Jim Johnson, the numbers were still being crunched. But he pointed to a few significant details. For one: Projects are getting more expensive, and big projects are more likely to fail.
For another: As projects get bigger, we're no longer keeping our work iterative. We've gone back to more traditional development practices -- practices with higher failure rates.
For a third: Lack of user involvement has jumped back to the top position among reasons for IT project failure. But lack of executive support is still running a very close second. Without committed executive sponsors and involved users, our projects fail.
Johnson told me the key to success is scope management. If you can keep projects tight and focused, avoid bloated feature wish lists and watch out for explosive requirements such as, "The new system must do what the old system did," you can do OK.
Maybe he's right. But I think we need to do more than just avoid scope creep.
One reason I like the Chaos study is that Standish counts up the results of lots of real projects, and it has been doing that for long enough that we can see real trends. So we know that our biggest success rate for IT projects came right in the middle of the recent downturn. After the bubble burst, budgets were tight, resources were strained and big projects were rare.
And -- not coincidentally -- our success rate jumped and our project cancellation rate dropped. When projects are small, we succeed.
That suggests that we don't just need to keep projects from getting too big. We need to work actively to dismantle big projects.
Chop a big project down into smaller projects and three things happen. First, everything's simpler. We can use smaller, more focused teams. We can deal with a limited



- Excel 2010 Cheat Sheet
- Register for this Computerworld Insider Cheat Sheet and gain access to hundreds of premium content articles, guides, product reviews and more.
- Five Myths of Cloud Computing
- This white paper separates fact from fiction, reality from myth, and, in doing so, will aid senior IT executives as they make decisions...
- Smarter Commerce is redefining value chain visibility
- Smarter Commerce is redefining the value chain in the age of the customer. It starts with putting the customer at the center of...
- Digital Transformation: Creating New Business Models Where Digital Meets Physical
- Individuals and businesses alike are embracing the digital revolution. Social networks and digital devices are being used to engage government, businesses and civil...
- IBM Synchronizes its Commerce 2.0 Strategy with 'Smarter Commerce' Initiative
- On March 14, IBM announced "Smarter Commerce", a strategic initiative that addresses the surging market for Commerce 2.0 solutions that take advantage of...
- Identity Governance: The Business Imperatives
- This white paper describes the business challenges and opportunities that are driving interest in Identity Governance while discussing considerations your organization should make... All Project Management White Papers
- Optimizing Networks for the Cloud
- Join guest speaker, Rohit Mehra, IDC Director of Enterprise Communications Infrastructure, to explore current trends, discuss best practices for optimizing Data Center and...
- Apps QuickStart Series Part 2: Designing and Deploying SQL Server on VMware vSphere
- Download this webcast to learn about the design considerations for virtualizing SQL workloads, performance and scalability information and high-availability options, as well as...
- Apps QuickStart Series Part 1: Designing and Deploying Exchange 2010 on VMware vSphere
- Download this webcast to learn the virtual hardware design considerations for Exchange 2010, deployment using the building block approach, options for high-availability and...
- Customer Spotlight: How IPC The Hospitalist Company Implemented Oracle on VMware
- Have you been looking to hear about customer's experiences with the new VMware vCenter Site Recovery Manager product? View this webcast to learn...
- Virtualize Business-Critical Applications with Confidence
- Virtualizing business-critical applications has become a key focus for organizations as they move along their virtualization journey. With the launch of VMware vSphere®... All Project Management Webcasts