Multiprojecting: Progress by Illusion
Computerworld -
Your CIO has two projects he wants finished in the next month. "We can share this project manager and that test team on both of these high-priority projects," he declares confidently. "The projects are small enough that the teams should be able to make progress." Two weeks later, the CIO realizes neither project is progressing the way he'd envisioned. What's going on?
Quantity does not equal quality
"Those who speak most of progress measure it by quantity and not by quality." -- George Santayana
The short answer is that putting the same people on two high-priority projects only creates the illusion of progress by focusing on quantity of projects being worked on, not projects completed. Here's what really happened.
The project manager worked mornings on Project 1 and afternoons on Project 2. Part of the test group also chose to work mornings and afternoons. But the other part of the test group used Monday and Tuesday for Project 1 and the rest of the week for Project 2 because of the way they needed to work with the developers. The first problem was that the project team, including the project manager and the testers, didn't work on the same project at the same time.
The project manager and the testers maintained their time organization only for the first week. After the first week, the project manager was an obstacle to both projects, because he was working on one project when he was needed on the other. Work from Project 1 piled up when he was on Project 2 and vice versa. By the start of the third week, the project manager hadn't cleared any obstacles for either of the project teams.
The testers couldn't help the projects make progress either. One tester who split his project work into mornings and afternoons discovered a problem that required test data from one of the Monday/Tuesday testers. It was bad enough that the testers had to wait on one another for information, but the developers had to wait for the testers, too. The developers would start to fix problems, then have to wait more than a week for the testers to verify them.
In this case, the multiprojecting caused people to be far less productive than if they'd been assigned to only one project at a time.
The Case of Disappearing Time
"Time is an illusion. Lunchtime doubly so." -- Douglas Adams
People pay a context-switching cost when they switch from one project to another. Even if they try to assign half of
Development
Additional Resources



Learn the important issues you must consider before starting your next mobility initiative. Get your mobility white paper from IDC now, compliments of Sybase.
White Papers & Webcasts
Extend, Replace, or Convert; which is the best way forward for COBOL Applications?
Download this white paper, free, compliments of Micro Focus!
Forrester Consulting - Optimizing Users and Applications in a Mobile World
Learn how to successfully deploy a WAN optimization solution that is specifically tuned for a mobile environment!
Effectively Implementing Datacenter Automation
Effectively select and deploy the best datacenter automation solution today!
Faster, Cheaper and Easier to Maintain
Can you afford not to upgrade your servers to today's advanced, energy-efficient technologies?
Aligning IT to Business: The Rising Importance of Application Delivery Networks
Application Delivery Networking (ADN) will play a vital role in helping enterprises incorporate strategic technologies to achieve business initiatives.
The State of PCI DSS Compliance at Organizations Today
Download this resource today!
IDC Research Report: The Business Value of Consolidating on Energy-Efficient Servers
Download this Resource Now!
Mitigate Risk, Lower Costs and Improve Network Efficiency
Create a stable IP network that not only meets today's challenges, but is flexible enough to also meet future demands.