Auditors: Army's huge SAP project 'at high risk'
IDG News Service - The U.S. Army's massive SAP software project is "at high risk" of running further over time and budget, according to a recent report by the Department of Defense's Inspector General's Office.
Auditors sought to determine whether DoD and Army officials managing the project had taken the proper steps to fix problems identified in a 2008 report by the Inspector General's Office, according to the report, which was released last month.
Their actions were insufficient, auditors found. "The Army estimates it will spend $2.4 billion over the [project] life cycle; however, it still has not identified all of the requirements and costs associated with the project," the report stated. "In addition, the DoD and Army did not implement 7 of the 16 recommendations we made in our prior report."
The SAP project, which is called the General Fund Enterprise Business System (GFEBS), will manage a $140 billion annual budget and serve nearly 80,000 users once it is complete. Some 15,500 users are now live on the system.
It has already seen delays and more than $53 million in cost overruns, according to the auditors' report. An initial "operational capability" milestone first set for August 2007 was pushed back to September 2010, it stated. A proposed December 2009 target date for "full operational capability" was moved to December of this year, it added.
There's also the chance that the system, once implemented, won't meet its original objectives, according to the auditors' report. Between June 2005 and September 2009, testing requirements more than doubled from 314 to 634.
"Complete and accurate program requirements are critical because GFEBS will interface with or replace at least 141 systems," the report said.
The system should not be deployed to additional users until the deficiencies are corrected, the auditors stated.
But comments from Army project managers who were included in the report downplayed the auditors' findings.
"The Army believes the risks identified in this report are manageable and do not materially impact the [project's] cost and schedule," said an official with the Assistant Secretary of the Army (Acquisition, Logistics, and Technology).
SAP "values its strong relationship with the United States Army, which continues to implement SAP software to enhance transparency, speed and real-time analysis in its operations," the vendor said in a statement. "Just last week, the Army deployed wave six of GFEBS to 12,000 users of the Army National Guard, and the Army is scheduled to deploy future waves of implementation." SAP declined further comment.
Accenture, which has served as a systems integrator on the project, did not immediately respond to a request for comment Friday.
Overall, the auditors' report came as little surprise to Michael Krigsman, CEO of Asuret, a consulting firm that helps organizations conduct successful implementations.


- Excel 2010 Cheat Sheet
- Register for this Computerworld Insider Cheat Sheet and gain access to hundreds of premium content articles, guides, product reviews and more.
- Establishing a Strategy for Database Security is No Longer Optional
- The options for securing increasingly valuable databases are very broad and deep, and can be confusing. This research provides an overview of three...
- Driving Secure Enterprise File Sharing and Syncing in the Enterprise
- GroupLogic's new activEcho is the industry's only secure Enterprise File Sharing and Synching solution that balances the need for simplicity for the end...
- The Enterprise File Sharing Option
- Enterprises and IT departments need to address several critical security issues when considering file sharing and syncing products. Many of today's solutions do...
- Activities Streams Base An Integrated Social Layer
- The enterprise social software market is exploding thanks to converging trends of consumerization, cloud, and mobile. In this must-read report, "The Forrester Wave:...
- Converged Infrastructure for Dummies
- As you know, everything is mobile, connected, interactive, and immediate. This is exactly why organizations need a highly agile IT infrastructure in order... All Applications White Papers
- Delivery Management -- Extending Lifecycle Management
- Date: Wednesday, June 20, 2012, 1:00 PM EDT
Siloed organizations continue doing the wrong things and doing things wrong, leading to increased costs,... - Leverage automation today to reduce IT complexity
- Date: Tuesday, June 5, 2012, 2:00 PM EDT
Whether your B2B complexity is caused by multiple technologies due to M&A, business or application specific... - BMC Control-M - Single Point of Control Demo
- With BMC Control-M, you schedule and manage everything - down to the very last platform and application - from one simple interface. It's...
- Operational Analytics - Changing the Competitive Dynamics of the Business
- Date/Time: June 5, 2012, 11:00 a.m., EDT, 4:00 p.m. BST / 3:00 p.m. UTC
Please join us for this webcast, as Dr. Barry... - Oracle Database Appliance Best Practices
- Business users increasingly demand 24x7 availability of their data while IT departments face the challenge of ensuring maximum availability while operating with limited... All Applications Webcasts