Firing Your Project Sponsor
A dysfunctional executive sponsor can pull your project down. Here's how to cut him loose.
February 23, 2004 12:00 PM ETComputerworld -
The $9 million project was behind schedule because the executive sponsor was incompetent. "He was a very nice guy," recalls the project manager, Virginia Robbins, who's now director of IT at a different company, Chela Financial Cos. in San Francisco. "But he got caught up in details."
Robbins talked to the sponsor's boss about her problems with the sponsor's performance, but the boss asked her to continue muddling through. As weeks passed, she became increasingly worried. Finally, she asked the sponsor's boss to meet her for lunch and helped him understand that the sponsor's failure would soon be his failure. "I pulled out our plan, showed him our progress to date and explained why we would be six months late," she recalls. Soon after, the sponsor was replaced.
The project sponsor is the executive or manager with the fiscal authority, political clout and personal commitment to see a project through . An effective executive sponsor can remove barriers and get key support for an IT project. But some sponsors -- whether from flagging interest, overwork or unsuitability for the job -- turn out to be so dysfunctional or underperforming that they drag the project down.
"We've seen sponsors ditching projects, or they do a slow withdrawal from the project," says Gopal Kapur, president of the Center for Project Management in San Ramon, Calif. "They don't meet with the project managers or do what they need to do."
But replacing an underperforming sponsor is a dangerous game. "It's politically touchy," says Catherine Tomczyk, a project manager at First Data Corp. in Greenwood Village, Colo. "It's risky because if the sponsor is in a position to cause you pain, he might."
Here are some strategies for getting a bad project sponsor out of your way:
Plan Ahead
Work upfront to be sure you get a great sponsor from the beginning, says Neil Love, author of The Project Sponsor Guide (Project Management Institute, 2000). "It's easier to influence the choice than to have to fix it later."
Sign a Prenup
When the project charter is signed, meet privately with the sponsor and hammer out the procedure you will follow in case of inadequate performance, Kapur suggests. Follow it up in writing. Later, if things go wrong and you begin to talk to others about the sponsor's performance, "you're not going behind the sponsor's back," he says. "You're just following the process agreed upon in first place."
Give Him an Easy Out
State in the sponsorship agreement that if the sponsor can't fulfill his
Project Management
Additional Resources



White Papers & Webcasts
Top 10 Habits of Highly Effective PMOs
Download This Whitepaper Now!
The Commercialization of ITIL: Lessons Learned
Register for this event today!
Your Solution for Delivering and Optimizing Applications Across the Enterprise
Download this whitepaper. Brought to you by Citrix.
Key Strategies for Managing Data Growth
What are you storage challenges?
Application Delivery Solutions
Download this whitepaper. Provided to you by Citrix.
Extending Client Refresh - 11 Steps to Maximize Savings
Register Now!
8 Must-Have Features to Handle All of Your Network Demands
Download this whitepaper. Provided by Citrix.
Lower the Cost and Complexity of a Mobile Workforce through Automation
Download This Resource Now!
Data Manager Report Excerpt: File System Inventory
Cut storage costs and boost operational efficiencies.
Managing Mobility: Improve Data Security, Compliance and Manageability
Download This Resource Now!


