Computerworld - After three years of work and $18 million spent, Philadelphia still has not deployed a water billing system for its half-million customers and is now working with Oracle Corp. -- the major vendor behind the project -- to get it back on track.
The billing system, Project Ocean, was designed in 2003 to replace a 30-year-old, custom-built operation that relies on outdated technologies and fails to collect all the revenue it should, according to city officials and records. It has taken two years longer than planned and more than twice as much money as initially projected.
The effort stumbled because of technical complexity, changes of administrators overseeing the rollout and Oracle's inexperience building such a system, according to critics and Philadelphia CIO Dianah Neff. The current talks with Oracle are taking place even as Neff prepares to leave her job Sept. 8 -- before the negotiations are expected to be done.
Neff, who has pushed Philadelphia's municipal Wi-Fi effort and is about to start a WiFi-focused consulting job in another city, said Project Ocean is on hold until the Mayor's Office of Information Services (MOIS) and other city officials can reach "settlement that will put the project back on track." She said the project could be modified or replaced by a "workable solution" to protect the city's investment "and deliver a modern utility and collection system within 18 months."
An Oracle spokeswoman said only that the implementation is "still in progress, and Oracle believes that the work performed to date conforms with the current agreement." She said the vendor will deliver on its obligations to complete the project.
City Controller Alan Butkovitz said his office is midway into a review of what happened with Oracle and Project Ocean, but added that it is too soon to speculate on what went wrong. Meanwhile, he said, "anything the city administration does to make sure there's a workable product for its money is commendable, and we wouldn't get in the way of that."
One Project Ocean critic, former City Water Commissioner Kumar Kishinchand, said he never felt the project would work when it was discussed in 2002 and 2003. He left the commission in 2004 after 12 years.
"One reason is that they picked a company that had never done a water billing system," Kishinchand said yesterday. "Oracle had only done viable customer service systems with a small portion for billing purposes. Municipal billing systems tend to be tremendously complex."
The off-the-shelf components of such systems have to be heavily modified, a complex and time-consuming effort, he said.
Kishinchand also argued that project managers "did not have much to lose if it failed," since the city's Finance Department would be in charge -- not the Water Department, which is the principal operator and user of the system. "The city's Water Department could have managed to tweak it to get it to work, because they had a compelling interest to get it to work."



- Excel 2010 Cheat Sheet
- Register for this Computerworld Insider Cheat Sheet and gain access to hundreds of premium content articles, guides, product reviews and more.
- Virtualizing Government Infrastructure
- All server virtualization solutions are not created equal. The more-with-less agenda for government agencies is tailor-made for server virtualization, which is evolving into...
- Overcome Top 7 Admin Challenges of Active Directory
- As Active Directory's role in the enterprise has drastically increased, so has the need to secure the data. Gain insight on creating repeatable,...
- Insiders Can Ruin Your Company. Take Action.
- Did you know that 80 percent of threats to an organization come from the inside? The threat from insiders is often overlooked in...
- Top Solutions and Tools to Prevent Devastating Malware
- Custom malware frequently goes undetected. According to Forrester Research, the best way to reduce risk of breach is to deploy file integrity monitoring...
- Streamline Compliance and Increase ROI
- Streamline, simplify, and automate compliance related activities; especially those that impact multiple business units. This white paper from NetIQ, outlines solutions that will... All IT in Government White Papers
- Optimizing Networks for the Cloud
- Join guest speaker, Rohit Mehra, IDC Director of Enterprise Communications Infrastructure, to explore current trends, discuss best practices for optimizing Data Center and...
- Apps QuickStart Series Part 2: Designing and Deploying SQL Server on VMware vSphere
- Download this webcast to learn about the design considerations for virtualizing SQL workloads, performance and scalability information and high-availability options, as well as...
- Apps QuickStart Series Part 1: Designing and Deploying Exchange 2010 on VMware vSphere
- Download this webcast to learn the virtual hardware design considerations for Exchange 2010, deployment using the building block approach, options for high-availability and...
- Customer Spotlight: How IPC The Hospitalist Company Implemented Oracle on VMware
- Have you been looking to hear about customer's experiences with the new VMware vCenter Site Recovery Manager product? View this webcast to learn...
- Virtualize Business-Critical Applications with Confidence
- Virtualizing business-critical applications has become a key focus for organizations as they move along their virtualization journey. With the launch of VMware vSphere®... All IT in Government Webcasts