What's Wrong With Wednesdays?
Computerworld - Many of the project schedules I review contain milestone completions on Fridays and new task or phase beginnings on Mondays. With a Friday or Monday milestone, what you're really saying is that people can work overtime all week and all weekend to make the Friday milestone, so they won't be late for the Monday start.
Why? Why do we do this to ourselves and to our project teams?
It's convenient to think about project milestones ending on Fridays and new things starting on Mondays. But just because it's more convenient from a calendar perspective, should we use Fridays and Mondays to end and begin project segments?
I say no. Down with Fridays and Mondays. Let's end and begin project segments on Wednesdays. Wednesday is a perfectly good day, and one that is possibly underutilized in project planning. Tuesdays and Thursdays are also good, and in my experience, underutilized. Here are the effects we might see if we choose a Wednesday to end a project phase or start a new phase.
- Improve schedule precision. We would know that our schedule estimations are wrong, and we might know more about how we estimate incorrectly. When we hide the actual milestone complete dates behind massive overtime, we encourage our project staff to inaccurately predict the next schedule, leading to even more overtime. Here's why: When we schedule project phases to complete on Fridays, we allow ourselves to take the weekend to complete the pieces not quite done on Friday. Completing a phase on Friday really means the phase is complete by the time people get to work on Monday morning. If we don't complete the work by Monday morning, then we're honest-to-goodness late. But, if we completed the work on Sunday morning, are we truly late? In reality, yes! We have underestimated the work, and we need to know about that underestimation to improve our estimation the next time. Otherwise, we can continue to underestimate projects by however much we are underestimating them now.
- Adjust for schedule risk sooner. We would know earlier in the project that the project has a higher risk than we earlier believed of not meeting its release date. The earlier in the project you know that the project is in trouble, the more options you have. At the beginning of the project, you can still add more staff, change tools, drop features, modify your life cycle, change how you work to reduce defects, or choose to allow more defects. In the middle of the project, you may be able to add more staff, drop features, change how you work to reduce defects or choose to allow more defects. At the end of the project, you can drop features or choose to allow more defects. As a project manager, I want to have more options rather than fewer when I'm faced with schedule-related bad news.
![]() ![]() | |
| Johanna Rothman consults on managing high technology product development, focusing on project management, risk management and people management. |



- Excel 2010 Cheat Sheet
- Register for this Computerworld Insider Cheat Sheet and gain access to hundreds of premium content articles, guides, product reviews and more.
- The Keys to Distributed & Agile Application Development
- How leading firms are winning with strategies for efficient application development, without relying on co-location.
- Overcome Top 7 Admin Challenges of Active Directory
- As Active Directory's role in the enterprise has drastically increased, so has the need to secure the data. Gain insight on creating repeatable,...
- Insiders Can Ruin Your Company. Take Action.
- Did you know that 80 percent of threats to an organization come from the inside? The threat from insiders is often overlooked in...
- Top Solutions and Tools to Prevent Devastating Malware
- Custom malware frequently goes undetected. According to Forrester Research, the best way to reduce risk of breach is to deploy file integrity monitoring...
- Streamline Compliance and Increase ROI
- Streamline, simplify, and automate compliance related activities; especially those that impact multiple business units. This white paper from NetIQ, outlines solutions that will... All App Development White Papers
- Reduced TCO for Communications Applications with New Oracle SPARC Servers
- In this webcast learn how Oracle's new SPARC T4 servers and SPARC Supercluster deliver the security, performance, and scalability required for 4G network...
- Optimizing Networks for the Cloud
- Join guest speaker, Rohit Mehra, IDC Director of Enterprise Communications Infrastructure, to explore current trends, discuss best practices for optimizing Data Center and...
- Apps QuickStart Series Part 2: Designing and Deploying SQL Server on VMware vSphere
- Download this webcast to learn about the design considerations for virtualizing SQL workloads, performance and scalability information and high-availability options, as well as...
- Apps QuickStart Series Part 1: Designing and Deploying Exchange 2010 on VMware vSphere
- Download this webcast to learn the virtual hardware design considerations for Exchange 2010, deployment using the building block approach, options for high-availability and...
- Customer Spotlight: How IPC The Hospitalist Company Implemented Oracle on VMware
- Have you been looking to hear about customer's experiences with the new VMware vCenter Site Recovery Manager product? View this webcast to learn... All App Development Webcasts