What's Your Fault Feedback Ratio?
Computerworld -
Most of us track faults (also called defects, problems, issues, bugs) during the system test part of the project. However, many project managers don't track how many of our fixes are successful and how many fixes are bad -- either introducing a new defect or not completely fixing the original defect. If you're looking for better scheduling of your system test and project completion, start measuring your Fault Feedback Ratio, the FFR.
Here's how to calculate your fault feedback ratio:
| Fault Feedback Ratio = | Fixes that require more work |
| All the fixes |
When I've measured successful projects, the FFR stays under 10% throughout the project, meaning that no more than one in 10 fixes are problematic as the work progresses. (Don't be deceived by a low FFR and a high overall fault count. With a large total count, the defects can be too overwhelming to successfully manage.) A low FFR and a not-too-high overall defect count also implies that the developers have a relatively easy time finding and fixing the problems. The testers don't have too much trouble keeping up with testing the fixes, because the fixes haven't broken other pieces of the software. The project team is progressing.
On the other hand, an FFR of 15% or higher means that people are spending significant time finding and fixing problems. A higher FFR and a low defect count may mean that the problematic fixes are in the same part of the code base. A higher FFR and normal or high defect counts, may mean the developers may have trouble detecting where to fix the problems, and the testers may have trouble verifying the fixes are good.
Once the FFR hits 20%, you're making dubious progress on the project because your team is spending too much time re-fixing problems they thought were already fixed and retesting those fixes.
![]() ![]() | |
| Johanna Rothman consults on managing high technology product development, focusing on project management, risk management and people management. Join the online discussion about this column. |
By the time the project was supposed to start system test, the FFR was up to 23%. The project had met its previous milestones, but the team was unable to predict the
Development
Additional Resources



Learn the important issues you must consider before starting your next mobility initiative. Get your mobility white paper from IDC now, compliments of Sybase.
White Papers & Webcasts
Extend, Replace, or Convert; which is the best way forward for COBOL Applications?
Download this white paper, free, compliments of Micro Focus!
Data Manager Report Excerpt: File System Inventory
Cut storage costs and boost operational efficiencies.
Key Strategies for Managing Data Growth
What are you storage challenges?
Reducing Storage Costs with F5 ARX
Save money- deploy ARX Solutions.
Extending Client Refresh - 11 Steps to Maximize Savings
Register Now!
Southern Company
Download Now
Lower the Cost and Complexity of a Mobile Workforce through Automation
Download This Resource Now!
Defending Against the Storm
Download Now
Managing Mobility: Improve Data Security, Compliance and Manageability
Download This Resource Now!