'Viewing' the project
Computerworld -
It's an old joke that IT development projects are on track until a week before the deadline, at which point the customer discovers that the project is really six months behind schedule. The developers may have worked long hours, but it often turns out that nobody fully understands the status of their project deliverables.
One reason the status and deliverables are unknown is that the developers' processes are "hidden" from the project manager and end users; it's almost as if the developers were coding in the dark.
I learned the significance of this on a recent trip to India, which is rapidly becoming recognized as the center of software development excellence. Of the 10 software organizations in the world that had achieved a Level 5 rating on the Software Engineering Institute's (SEI) Capability Maturity Model scale last September, five were Indian. And an amazing 40% of the world's 59 high-maturity organizations (those at Level 4 or 5) are in India.
The scale provides the basic explanation of the "hidden process" dilemma. An organization at Level 1 has no defined process; hence, neither the developers nor the manager nor the customer knows what processes are being performed. In contrast, an organization at Level 3 or higher does have a defined process, and if anyone wants to see it, there's a document that describes it in detail. Good project management goes hand in hand with formal, disciplined processes that are carried out consistently; everyone knows what deliverables are associated with each activity and there should be very few surprises along the way.
But what about end users who have been burned on previous projects and who aren't passionate believers in SEI? They might ask, "How do I know that your developers are following a formal process?" If the project manager says, "Here's a description of the process, and it's the same one we followed on our last 10 projects," the cynical user might still say, "We don't care about your last 10 projects! How do we know you're following it this time?"
There are two familiar ways to answer this question: produce frequent prototypes throughout the project, and produce voluminous progress reports, updated weekly. But in today's "Internet time" environment, that may not be enough. A mission-critical e-business project may last only four weeks. If it takes a full week to find out that you're building the wrong system, you've already lost 25% of your time.
An alternative, as some of the best Indian software companies are demonstrating, is to make the
IT Management
Additional Resources



White Papers & Webcasts
Data Manager Report Excerpt: File System Inventory
Cut storage costs and boost operational efficiencies.
Extending Client Refresh - 11 Steps to Maximize Savings
Register Now!
Reducing Storage Costs with F5 ARX
Save money- deploy ARX Solutions.
Consolidate Your Servers and Storage to Lower Costs with Oracle Database 11g
Register for this webcast!
The Commercialization of ITIL: Lessons Learned
Register for this event today!
3 Minutes with Free Tool Can Save Thousands!
Register Now!
Key Findings: Accelerating ROI with BPM
Click here to watch now!
Looking for a fast payback?
Register Now!
