NASA's SAP Launch Drags

Inspector general blasts the $116M financial systems upgrade

March 27, 2006 12:00 PM ET

Computerworld - A major upgrade to the core financial systems of the National Aeronautics and Space Administration has encountered turbulence from end users and the agency's inspector general before getting far off the ground.

The $116 million financials upgrade is the cornerstone of a larger project, dubbed the Integrated Enterprise Management Program, which is expected to cost $1.1 billion. The IEMP uses R/3 financial applications from SAP AG, and when completed, it's expected to improve financial, contractual, asset management and other procedures throughout NASA.

However, critics claim that five years into the estimated eight-year project, the IEMP has suffered from end-user resistance, data integration problems and a lack of oversight.

Last month, NASA's Office of the Inspector General found flaws in the management of IEMP contracts and demanded improvement. "Despite the criticality of IEMP to the agency, NASA's monitoring of the contracts was informal and inadequate to ensure that IEMP products and services were procured in a satisfactory, cost-effective manner," according to the report.

For example, the report stated that as of September 2004, five of 14 SAP-related projects, worth $16.5 million, were for services not even officially funded. The inspector general's office warned that the lack of centralized oversight could impede NASA's ability to manage the contracts, and it urged that a single set of vendor policies be established.

End-User Concerns

End users of the software have concerns about the project, said Lee Stone, vice president of legislative affairs for NASA's union, the International Federation of Professional and Technical Engineers of the AFL-CIO and the Canadian Labour Congress. The organization has been critical of the IEMP and believes that the biggest problem is the way it imposes complex accounting processes, he said.

There are also various technical problems, including integration gaps between SAP and other applications, such as NASA's workforce management system. The SAP software can be hard to use, and it's not clear that it's boosting productivity, Stone said.

"It remains unlikely that NASA will achieve a clean audit again this year, despite the fact that SAP went live back in October of 2003," he claimed.

Patrick Ciganer, the program's executive officer, didn't deny the project's complexity and the technical and personnel-related challenges. "It's been very tough, because we were an early [federal] adopter and we've been under a lot of scrutiny by oversight organizations. There have been a lot of challenges," he said.

Ciganer said that the inspector general's criticisms were largely related to procurement and that those issues haven't affected the technology. He also said that since the core financials system went live in 2003, it has generally worked as anticipated.

However, Ciganer noted, the system did require some work-arounds. It replaced 150 custom-built applications that supported NASA's various organizations, he said, and the data-conversion process was extremely difficult.

Ciganer also acknowledged that there was some end-user resistance. "This is NASA. We have very smart people. You can't just say, 'It will be better for you,' " he said. For its part, SAP said in a statement that the overall project is a challenging one, but "in the long run NASA will benefit by becoming a more efficient agency." SAP will continue to work with NASA to "make this process design a success," it said.

NASA’s Costly Liftoff

CORE FINANCIALS: SAP R/3 4.6


RUNS ALL 10 NASA facilities


NASA PLANS UPGRADE to mySAP ERP in 2007


BY JANUARY 2005 82 IEMP contracts worth $630M awarded to 29 firms


FINAL PRICE TAG: $1 billion-plus

Source: NASA

Read more about it in government in Computerworld's IT in Government Knowledge Center.



Jump to comments

International Federation of Professional

Additional Resources

EFD vs. HDD - What You Need to Know
WHITE PAPER
Enterprise flash drives provide a new Tier 0 storage layer capable of delivering high I/O performance at a very low latency. Proper use of EFDs in an Oracle environment can deliver increased performance compared to fibre channel drives. Read the recommendations for identification of the best DB components for EFDs.
Gartner Research Report: Magic Quadrant for Application Delivery Controllers, 2009
WHITE PAPER
The market for products to improve the delivery of application software over networks remains dynamic and innovative. Vendors focused on solving enterprises' most-pressing application problems have become the top players.
Eight Criteria for Server Load Balancing
WHITE PAPER
Server load balancers are a simple yet highly effective means to scale an application environment while ensuring its availability. Today's solutions should also address application performance and security. Read about the top eight criteria you should consider when choosing a server load balancer and how Citrix NetScaler meets those requirements.

What People Are Saying

White Papers & Webcasts

Insight from an Auditor: Ensuring a Successful PCI Audit
Ensure a successful PCI audit. Watch this webcast now.

IT Governance Podcast: IT Provider Forecasts $10 Million in Savings
In this podcast, learn how OTS was able to prioritize, then deliver, on the mission-critical demands and, in the process, project $10 million...

A New Approach to IT Governance
This 5-Minute Demo shows a new approach that lets IT quickly and easily realize the benefits of IT Governance.


IT Jobs