NASA's SAP Launch Drags

Inspector general blasts the $116M financial systems upgrade

March 27, 2006 12:00 PM ET

Computerworld - A major upgrade to the core financial systems of the National Aeronautics and Space Administration has encountered turbulence from end users and the agency's inspector general before getting far off the ground.

The $116 million financials upgrade is the cornerstone of a larger project, dubbed the Integrated Enterprise Management Program, which is expected to cost $1.1 billion. The IEMP uses R/3 financial applications from SAP AG, and when completed, it's expected to improve financial, contractual, asset management and other procedures throughout NASA.

However, critics claim that five years into the estimated eight-year project, the IEMP has suffered from end-user resistance, data integration problems and a lack of oversight.

Last month, NASA's Office of the Inspector General found flaws in the management of IEMP contracts and demanded improvement. "Despite the criticality of IEMP to the agency, NASA's monitoring of the contracts was informal and inadequate to ensure that IEMP products and services were procured in a satisfactory, cost-effective manner," according to the report.

For example, the report stated that as of September 2004, five of 14 SAP-related projects, worth $16.5 million, were for services not even officially funded. The inspector general's office warned that the lack of centralized oversight could impede NASA's ability to manage the contracts, and it urged that a single set of vendor policies be established.

End-User Concerns

End users of the software have concerns about the project, said Lee Stone, vice president of legislative affairs for NASA's union, the International Federation of Professional and Technical Engineers of the AFL-CIO and the Canadian Labour Congress. The organization has been critical of the IEMP and believes that the biggest problem is the way it imposes complex accounting processes, he said.

There are also various technical problems, including integration gaps between SAP and other applications, such as NASA's workforce management system. The SAP software can be hard to use, and it's not clear that it's boosting productivity, Stone said.

"It remains unlikely that NASA will achieve a clean audit again this year, despite the fact that SAP went live back in October of 2003," he claimed.

Patrick Ciganer, the program's executive officer, didn't deny the project's complexity and the technical and personnel-related challenges. "It's been very tough, because we were an early [federal] adopter and we've been under a lot of scrutiny by oversight organizations. There have been a lot of challenges," he said.

Ciganer said that the inspector general's criticisms were largely related to procurement and that those issues haven't affected the technology. He also said that since the core financials system went live in 2003, it has generally worked as anticipated.



Jump to comments

IT in Government

Additional Resources

WHITE PAPER
Approximately 60 percent of data migration projects overrun time or budget, while some fail completely. Download this white paper, "Enhancing Your Chance for Successful Data Migration," to learn the critical steps you need to take to execute a data migration project with minimum cost and risk to your business.
WHITE PAPER
Read the Gartner research note to learn why the TCO of a server-based computing deployment used to deliver all applications to users is around 50% lower than that of an unmanaged desktop deployment.
WHITE PAPER
Economic downturns have a tendency to accelerate emerging technologies, boost the adoption of effective solutions, and punish solutions that are not cost competitive or that are out of synch with industry trends. This IDC White Paper presents the results of an IDC survey of 330 companies in Western Europe, Asia/Pacific and the Americas that measures the receptiveness to Linux and takes into consideration changing views driven by the disruptive economic environment that businesses face today.

White Papers & Webcasts

Data Manager Report Excerpt: File System Inventory
Cut storage costs and boost operational efficiencies.  

IT Governance Podcast: IT Provider Forecasts $10 Million in Savings
In this podcast, learn how OTS was able to prioritize, then deliver, on the mission-critical demands and, in the process, project $10 million...

Reducing Storage Costs with F5 ARX
Save money- deploy ARX Solutions.  

A New Approach to IT Governance
This 5-Minute Demo shows a new approach that lets IT quickly and easily realize the benefits of IT Governance.

Southern Company
Download Now  

Key Strategies for Managing Data Growth
What are you storage challenges?

Share our Strength
Download Now