How to Write a Progress Report

Everyone does it, but few do it well. Here's how.

December 19, 2005 12:00 PM ET

Computerworld - In any given month, Sue Schade sees 20 to 30 progress reports, and she needs to digest the information as quickly as possible.
Schade, CIO at Brigham and Women's Hospital in Boston, knows what she wants to see and how she wants to see it, and she makes her expectations crystal clear to those who report to her.
She expects to know what has been accomplished, which key decisions have been made, what's going on now, what's on the horizon and which issues are in play. She also wants to know whether projects are on track to meet their original deadlines. And she wants it all in a standard format. "My folks know what they have to put in," Schade says. "I don't want to look at a lot of different formats and ask, 'Where's this? Where's that?'"
Progress reports are essential tools for tracking projects and initiatives, but if the writers and readers aren't in sync, reports can be hit-or-miss exercises for everyone involved. Here are some tips on how to deliver the right information to the right people at the right time.
Set Expectations
Different people want different kinds of reports. One CIO might want a page of narrative, while another might want "a set of graphs and two bullet points," says Kevin Doyle.
"It depends on the situation, what the receiver is comfortable receiving and how you can best communicate with him," says Doyle, an associate professor of business administration at Benedictine University in Lisle, Ill.
Doyle, who has overseen corporate IT initiatives, says project managers should establish expectations at the start by determining who will get reports, how often and in what form.
Jason Fortier, director of the CRM service line at Adjoined Consulting Inc. in Miami, agrees. He's currently working with one company on a project that affects five business units, so he built a report template early on, shared it with division leaders and asked each whether he'd need anything else in the reports.
Fortier says a project's size, scope and phase help determine the frequency of reports. Projects in the analysis phase, for example, don't require weekly reports, but initiatives in the middle of implementation usually do, he says.
Nail Down the Essentials
It's up to you as project manager to find out what executives want in progress reports. When Rosalee Hermens reads a report, for example, she wants to see updates on the technology, finances, schedule, design and management, and she wants to compare those items over time. "I want to see



Jump to comments

IT Management

Additional Resources

EFD vs. HDD - What You Need to Know
WHITE PAPER
Enterprise flash drives provide a new Tier 0 storage layer capable of delivering high I/O performance at a very low latency. Proper use of EFDs in an Oracle environment can deliver increased performance compared to fibre channel drives. Read the recommendations for identification of the best DB components for EFDs.
Gartner Research Report: Magic Quadrant for Application Delivery Controllers, 2009
WHITE PAPER
The market for products to improve the delivery of application software over networks remains dynamic and innovative. Vendors focused on solving enterprises' most-pressing application problems have become the top players.
Eight Criteria for Server Load Balancing
WHITE PAPER
Server load balancers are a simple yet highly effective means to scale an application environment while ensuring its availability. Today's solutions should also address application performance and security. Read about the top eight criteria you should consider when choosing a server load balancer and how Citrix NetScaler meets those requirements.

IT Jobs

 

Putting the Right Model in Place to Better Balance IT Supply and Business Demand
IT leaders manage business demands and IT resources in many ways, but which methods are most effective? Tom Welsh, senior consultant of Cutter Consortium, compares two approaches and outlines their pros and cons in this Compuware-commissioned white paper. Get objective appraisals and real-world examples for both.

Download this white paper 
CIO best practices: Optimizing your Project Portfolio Management solution for greater business value
A Project Portfolio Management discipline goes beyond ordinary project management to link IT with the business and help IT leaders better understand the benefits, cost, risks and value of all projects. Download this Compuware white paper and learn how to boost the business value of your IT organization.

Download this white paper 
Exclusive eBook: Six Project Metrics Every CIO Should Know for Application Delivery Success
Most IT organizations spend their time measuring whether projects are on time or on budget. Read this IT executive guide to learn what key data tells you the degree of quality, client satisfaction and how well requirements were met. Make these metrics part of your overall application delivery management process - and your software can't fail.

Download this eBook 
IT Planning and Control: Unveiling the Interrelationships between ALM and PPM
Listen in as Gartner Analyst Matt Light discusses two hot topics-- Project Portfolio Management and Application Life-cycle Management--and how you can bring these disciplines together to improve application quality and delivery. Get recommendations on merging the two methods and learn what type of results you can expect.

Download this podcast