Sidebar: Managing Chaos

By Robert L. Mitchell
October 3, 2005 12:00 PM ET

Computerworld - When 270 artists moved into Industrial Light and Magic's new San Francisco headquarters over one weekend in August, they faced an environment where everything was different. From how to get into the building to where shared printers were located, everything would be disorienting.
"People were going to be terribly confused when they came into the parking garage," says Kevin Clark, director of IT operations. But he wanted their workstations to be the one "familiar zone" they could count on. So he challenged his group to present users with fully operational systems that would operate just as they had before the move.
He outsourced the physical move and setup of the machines so his staff could focus on testing. "That was critical because we didn't have the manpower [to do both]," Clark says.
Then he carved up the old and new facilities into geographic areas and assigned zone leaders who were responsible for the end-to-end move of IT equipment in each area.
At the old facility, the staff photographed each office and taped the image to the desktop prior to the move. When equipment arrived, the setup was checked against the photograph to ensure the placement was as consistent as possible.
Then the staff began testing each system, following a "hot-sheet" checklist that included items such as a physical cabling check and connectivity test. Add-on devices such as mice and graphics tablets were also tested. "In this environment, there are some funky setups. Some people have two or three mice, and there are [graphics] tablets," he says. The staff tested them all.
As the staff began testing, the zone leaders made sure everything was checked methodically. "It's easy to get ahead of yourself, so you want to move one step at a time," Clark says. "We touched everything several times and made sure everything worked." Once tests were completed, the hot sheet was taped to each system's monitor.
The staff had also gained valuable experience from previous moves in the multiphase project. "The biggest thing we learned is to include our service desk in the process," he says. Using two-way radios, the staff logged trouble tickets so the service desk could track problems as they were encountered over the weekend.
"That put [the service desk] in a much better position to support the move the following week," he says.
The planning paid off. When people began arriving Monday morning, they focused on orienting themselves to the office's physical layout and concerns such as the location of shared printers. Then they satdown at their desks. "They were back to work by 10:00 a.m.," he says.
There were a few minor issues. For example, when testing, the staff logged on with administrator privileges, so some problems based on local profiles didn't show up until the users arrived. But most people were immediately up and running.
"We haven't had any significant downtime, and this is an environment where we have a new phone system, new gear, and it's all working," Clark says, adding, "I think we have exceeded expectations."

Read more about Data Center in Computerworld's Data Center Topic Center.



Additional Resources
Forrester Consulting - Optimizing Users and Applications in a Mobile World
WHITE PAPER
Solving application issues over the WAN requires careful consideration. Based on their independent research, Forrester Consulting offers recommendations on how to tackle application performance issues, insufficient bandwidth and the inability to quickly restore users in a disaster.

Read now.

Security KnowledgeVault
WHITE PAPER
Security is not an option. This KnowledgeVault Series offers professional advice how to be proactive in the fight against cybercrimes and multi-layered security threats; how to adopt a holistic approach to protecting and managing data; and how to hire a qualified security assessor. Make security your Number 1 priority.

Read now.

Cut Communications Costs Once and for All
WHITE PAPER
New IP-based communications systems are being deployed by small and midsized businesses at a rapid rate. Learn how these organizations are enabling faster responsiveness, creating better customer experiences, speeding office or mobile interactions, and dramatically reducing existing communications costs.

Read now.

Data Center White Papers
Optimize Data Backup to Ensure Data Protection
Protecting data, a top IT priority, is made even more difficult as rapid data growth pushes traditional backup processes beyond their capabilities. Integrating...
Enabling Storage Flexibility to Better Manage Data Growth
Virtualizing file storage gives organizations the flexibility and data mobility required to reduce backup windows and costs, improve storage efficiency, and seamlessly integrate...
Case Study: Publisher Cuts Backup Times by 98 Percent
Learn how John Wiley & Sons, Inc., a leading publisher for scientific, technical, and medical communities, successfully reduced backup times from 36 hours...
Case Study: Firm Optimizes Storage, Shrinks Backup Window
By optimizing its existing storage environment, multi-skilled architectural firm RHWL reduced backup times from 14 hours to 1.5 hours, slashed tape and offsite...
Indiana University Virtualizes Mission-Critical Oracle Databases
The Kelley School of Business at Indiana University deployed VMware Infrastructure which decreases costs, streamlines server deployment, and reduces energy consumption.
All Data Center White Papers
Data Center Webcasts
Live Webcast
North Pole to South Seas: Overcoming the Pitfalls of remote Performance
In today's always-on world, connectivity is a business requirement. You need the tools that allow you to operate as if you were on...
Live Webcast
Playing Defense: Staying on Top of Your Disaster Recovery Game
When it comes to disaster recovery, rapidly growing data volumes, distributed computing models, and new technologies all combine to present an ever-changing playing...
Customer Spotlight: How IPC The Hospitalist Company Implemented Oracle on VMware
Have you been looking to hear about customer's experiences with the new VMware vCenter Site Recovery Manager product? View this webcast to learn...
Introduction to VMware View 5
VMware View™ 5 simplifies IT management while increasing end user freedom by delivering desktop services from your cloud. Building upon VMware's leadership in...
Reliable Disaster Protection with VMware vCenter Site Recovery Manager
A simple, cost-effective disaster-recovery solution for virtual environments is high on the agenda for IT organizations as they virtualize more business-critical applications with...
Introduction to VMware vCenter Site Recovery Manager 5
Traditional disaster recovery solutions are often too expensive, complex and unreliable to meet business requirements. As a result, IT departments are hesitant to...
Introduction to Virtualization
This video webcast is designed to help those with little to no virtualization experience understand why virtualization and VMware are so important to...
All Data Center Webcasts
Newsletter Sign-Up

Receive the latest news test, reviews and trends on your favorite technology topics

Choose a newsletter
  1. View all newsletters | Privacy Policy
IT Jobs