Development Study: Haste Makes Waste

September 23, 2005 12:00 PM ET

Computerworld - One of the supposed truisms of software development is that out of three attributes -- fast, good and cheap -- you can pick only two. Turns out the data from a recent research project says otherwise. Spending more money makes little difference in speed and actually reduces quality.

Quantitative Software Management (QSM) maintains the most comprehensive database of software development project metrics that I know of, including over 7,200 projects spanning almost 30 years. Its data comes from its own projects as well as the repository of an estimation product called SLIM. These projects are 58% IT projects (finance, human resources, etc.), 28% engineering (scientific, process control, etc.) and 14% real-time embedded systems (firmware, hardware controllers, etc.).

Although I haven't used it yet, SLIM first came to my attention when a customer told me in total amazement that her planned six-month project was projected to be three months late by the SLIM model. Her management dismissed this projection, of course, but she quietly kept track of the project anyway ... only to discover it accurately predicted the final delivery within a two-day margin! Accurate estimating is one of a Holy Grail of software development, and what I like about the SLIM approach is that it's based on experience, not theory.

Anyway, QSM recently repeated a study it did in 1996 to measure the effect of adding resources to compress a delivery schedule. This is a common reaction to being in a hurry or panicking over delays: Think fast and good but not cheap.

It studied small teams (five or fewer resources) and large teams (20 or more resources) developing between 10,000 and 200,000 lines of code and took a number of measurements including lines of code developed, schedule progress and defect creation. What it found wasn't a surprise, because the results simply confirmed the 1996 findings, but they should surprise you.


The difference between a large team (29 resources) and a small one (2.5) developing 40,000 lines of code was only about 12 calendar days earlier delivery! It took 191 person-months of resources for the large team and only 40 person-months for the small team. The difference at $12,000 per person month was $1.8 million. Now of course that results in a business decision: If 12 days of product availability is worth more than $1.8 million, it may be worth the investment. But it is worth doing the math.

One reason for the nonlinear productivity was explained by the fact that large teams produced more than six times as many



Jump to comments

Development

Additional Resources

WHITE PAPER
Approximately 60 percent of data migration projects overrun time or budget, while some fail completely. Download this white paper, "Enhancing Your Chance for Successful Data Migration," to learn the critical steps you need to take to execute a data migration project with minimum cost and risk to your business.
WHITE PAPER
Read the Gartner research note to learn why the TCO of a server-based computing deployment used to deliver all applications to users is around 50% lower than that of an unmanaged desktop deployment.
WHITE PAPER
Economic downturns have a tendency to accelerate emerging technologies, boost the adoption of effective solutions, and punish solutions that are not cost competitive or that are out of synch with industry trends. This IDC White Paper presents the results of an IDC survey of 330 companies in Western Europe, Asia/Pacific and the Americas that measures the receptiveness to Linux and takes into consideration changing views driven by the disruptive economic environment that businesses face today.