An Earned Value Management Project Primer

April 3, 2006 12:00 PM ET

Computerworld - Earned value management is based on several figures that are used to calculate a project's progress. You can measure in dollars or time.

Planned value (PV): This is the value of all resources needed to do the work to meet the project's objective. Although most project managers calculate PV in dollar terms, some calculate it in terms of time -- the number of hours it's expected to take to complete the project.

Let's take a very basic example. We've budgeted $200 to buy, set up, network and test a new system. We've budgeted $50, $75, $50 and $25, respectively, in materials, labor and other costs for those four phases.

Keep in mind, though, that the $50 set aside to buy the system doesn't just cover the cost of the actual hardware and software. It also takes into account the value of time that will be required to find the right system, the time that will be needed to fill out the purchase orders, the time it will take to actually buy the system and so on.

"The basis for earned value management is worked performed, not money spent," says Marilyn S. McCauley, owner of McManagement Group, an EVM consulting and training firm. Our PVs are $50, $75, $50 and $25.

Budgeted (cost) at completion (BAC): This is the sum of all PVs -- the total for all phases. In our example, BAC is $200.

Earned value (EV): As our team completes portions of the planned work, we check off that work and the amount of money (or time) it should have taken to do it according to the project plan. Project managers calculate EV at predetermined times based on the plan, typically at the end of the company's accounting period, McCauley says. We've completed Phase 1 -- buying the system -- within the planned time frame. Check that off as done. Our EV is $50.

Actual cost (AC): This can also be measured in dollars or time. In a perfectly executed project, EV and AC are the same. But in our example, let's say we actually used $60 in resources to buy that system. Our AC is $60.

Once you have these figures -- PV, BAC, EV and AC -- you can calculate other numbers that tell you about your progress on a project. Here are some of those calculations:

Schedule performance index (SPI): EV divided by PV for a particular phase of a project. In our example, that's 50/50 = 1, a perfect score for Phase 1, indicating that we're on target for schedule. "I said I'd do $50 worth of work, and I did $50 worth of work," McCauley says.



Additional Resources

POLL RESULTS
Accelerate your knowledge of the IT world you inhabit by viewing the results of a series of polls taken by your IT peers. These polls of 100+ IT professionals each are available for full viewing. They cover key topics such as virtualization, processor performance, green IT, cloud computing and many others. Be a part of the buzz.
WHITE PAPER
Technology is complex. Keeping it running productively shouldn't be. To that end, you want to minimize the number of solutions needed in-house to simplify operations, maintenance, and support. Kodak offers a best-practices model. One company provides support for both scanner and software, for fast problem resolution without vendor finger-pointing. Download now!
WHITE PAPER
Utilizing demand intelligence improves the precision of pricing, product assortments, channel/store placement, and promotion, which are all essential for sustainable revenue management performance. Learn more, download this free whitepaper today.

White Papers & Webcasts

Business Process Management: Leveraging Competencies and Streamlining Processes to Achieve Operational Excellence
(Source: IBM) BPM is a business management practice that encompasses process automation, process modeling and simulation, process modularization and service orientation, process monitoring,...  

BPM ROI calculator
(Souce: IBM) Content-rich processes, from opening a new account to customer billing, are central to day-to-day operations. These processes, however, tend to be...

Your Solution for Delivering and Optimizing Applications Across the Enterprise
Learn why a large US food processor chose Citrix NetScaler to securely deliver a new Oracle ERP solution to external partners and remote...  

BPM Survey Results: The Real-World Analysis
(Source: IBM) Business Process Management (BPM)enables faster, more confident decision making, which results in more transactions conducted, which ultimately leads to more satisfied...

Application Delivery Solutions
Learn why a $6.5 billion international producer and marketer of alcoholic beverages chose Citrix NetScaler to increase Web app performance and ensure high...  

Usability Is Everything
Learn what sets Workday's HR and Payroll solutions apart from the competition....

8 Must-Have Features to Handle All of Your Network Demands
The functionality you need in your next load balancer. Learn how you can replace your aging load balancer with a true web application...  

The Value of Real SaaS at Workday
Cost savings, speed to value, and innovation brought to the enterprise by Workday's software-as-a-service solutions for HR and Payroll....

Accelerate SSL Encrypted Applications
The amount of SSL traffic is growing in the enterprise. Because it is encrypted, it cannot be properly controlled and accelerated. Blue Coat...  

SaaS at Flextronics, Inc.
Dave Smoley, CIO of Flextronics, discusses the real value of software-as-a-service and why he chose Workday for his HR solution....

 

Putting the Right Model in Place to Better Balance IT Supply and Business Demand
IT leaders manage business demands and IT resources in many ways, but which methods are most effective? Tom Welsh, senior consultant of Cutter Consortium, compares two approaches and outlines their pros and cons in this Compuware-commissioned white paper. Get objective appraisals and real-world examples for both.

Download this white paper 
CIO best practices: Optimizing your Project Portfolio Management solution for greater business value
A Project Portfolio Management discipline goes beyond ordinary project management to link IT with the business and help IT leaders better understand the benefits, cost, risks and value of all projects. Download this Compuware white paper and learn how to boost the business value of your IT organization.

Download this white paper 
Exclusive eBook: Six Project Metrics Every CIO Should Know for Application Delivery Success
Most IT organizations spend their time measuring whether projects are on time or on budget. Read this IT executive guide to learn what key data tells you the degree of quality, client satisfaction and how well requirements were met. Make these metrics part of your overall application delivery management process - and your software can't fail.

Download this eBook 
IT Planning and Control: Unveiling the Interrelationships between ALM and PPM
Listen in as Gartner Analyst Matt Light discusses two hot topics-- Project Portfolio Management and Application Life-cycle Management--and how you can bring these disciplines together to improve application quality and delivery. Get recommendations on merging the two methods and learn what type of results you can expect.

Download this podcast