Moving Toward Meltdown
Ultradense 1U and blade server racks are blazingly fast -- and amazingly hot. Keeping them from burning up is more complicated than you might think.
October 6, 2003 12:00 PM ETComputerworld -
John Sawyer manages data centers for corporate clients every day. His company, Johnson Controls Inc., has plenty of experience in data center design and management. Nonetheless, the Milwaukee-based company's carefully designed and planned data center recently experienced overheating problems after installing blade servers.
Many data center managers are just beginning to contemplate large-scale deployments with multiple racks of ultracompact blade servers. These new systems take up far less space than traditional rack-mounted servers, but they dramatically increase heat density. Throwing multiple racks of them into a data center can result in problems ranging from outright failures to unexplained slowdowns and shortened equipment life.
"Today, because of the way the air handlers are configured, we can't handle more than 2 kilowatts per rack," says Sawyer, head of critical facility management services at Johnson Controls. Sawyer says new air-handling equipment can boost that figure into the 3-to-4-kw range. But new blade servers could consume 15 kw or more when fully loaded. That equates to more British thermal units per square foot than a typical household oven and requires a cooling capacity sufficient to air-condition two homes, facilities engineers say. So Sawyer can spread out the racks or partially fill each one to reduce overall wattage per square foot, or he can add localized, spot-cooling systems.
Although most data centers don't have many high-density racks today, data center managers are beginning to replace server racks with more compact designs, some of which accommodate more than 300 servers in a single 42U rack. (1U is 1.75 in.) "You can see a train wreck coming," says Kenneth Brill, executive director at The Uptime Institute Inc. in Santa Fe, N.M.
And while vendors say their systems are designed to run efficiently in fully loaded racks, they don't necessarily take into account the broader impact that large numbers of such racks will have on the rest of the data center.
"We can deal with one or two of these things, but we don't know how to deal with lots of them," says Brill.
The problem is compounded by two facts: Every data center is designed differently, and the industry has yet to agree on a standard for designing data center cooling systems that can handle 15 to 20 kw per rack.
The current guidelines from the American Society of Heating, Refrigerating and Air-Conditioning Engineers Inc. (ASHRAE) are outdated, says Edward Koplin, president of Jack Dale Associates PC, an engineering consulting firm in Baltimore. "Design engineers are using standards from the days of punch cards and water-cooled mainframes," he says. Atlanta-based ASHRAE is working hard on new thermal guidelines, says Don Beaty, chair of the group's High-density Electronic Equipment Facility Cooling Committee. He expects a published standard by year's end.
Additional Resources


White Papers & Webcasts
Hidden Cash: Maximizing the Value of Surplus Technology in a Down Economy
In today's tightened economy, all major technology purchases are being carefully scrutinized to ensure that each new piece of hardware and software can...
Usability Is Everything
Learn what sets Workday's HR and Payroll solutions apart from the competition....
Your Network at Half the Price: Slash Network Hardware Costs With Pre-Owned Equipment
Pre-owned networking equipment is certainly less expensive than the new variety, but IT managers are often challenged to know when and how to...
The Value of Real SaaS at Workday
Cost savings, speed to value, and innovation brought to the enterprise by Workday's software-as-a-service solutions for HR and Payroll....
Impact of the Dramatic Increase in Devices on the Cost to Support
This white paper describes the challenges that CIOs will face in coming years due to a dramatic increase in the number of devices...
SaaS at Flextronics, Inc.
Dave Smoley, CIO of Flextronics, discusses the real value of software-as-a-service and why he chose Workday for his HR solution....
Help Customers Preserve and Share Memories
As digital cameras became more and more prevalent, many photofinishers bemoaned the demise of their traditional film and processing business model. Digital posed...
Why Compliance Pays
This OnDemand webcast explores the relationship that firms with best compliance records have higher revenue, greater customer retention, lower financial losses from data...
For Best Results, Think Beyond the Box
Technology is complex. Keeping it running productively shouldn't be. To that end, you want to minimize the number of solutions needed in-house to...
Agile Enterprise Content Management (ECM) for Rapid ROI
Find out how combining ECM and BPM will help adress issues about content rich business processes....
Subscribe to Computerworld